Power is the next bottleneck
After GPUs, power has become the tightest bottleneck in AI infrastructure expansion. For decades, the US electricity system served largely flat demand; the spread of data centres is now adding gigawatts of new power demand every year.
Nearly 1,700 new data centres
Around 3,300 data centres are currently operating in the United States, with nearly 440 more under construction and over 1,200 planned. On the map, yellow indicates facilities under construction and blue those in the planning stage. New projects are typically much larger than existing facilities, and the location of the largest developments increasingly depends on available grid and generation capacity. This also explains the large number of megaprojects in Texas.
New data centres / Number of US data centres by lifecycle stage
The scarcity of power supply is evident in US grid operator PJM’s capacity auctions, which secure commitments from power plants to be available in future years. The clearing price rose more than elevenfold over two auctions and has remained at the price cap ever since. For the 2027/28 delivery year, the auction failed to secure even the capacity needed to ensure a reliable power supply. Increasingly severe imbalances are emerging in the electricity market.
PJM capacity prices remain stuck at the cap
PJM capacity auction clearing price, $/MW-day, by delivery year
Return Download
This is a marketing communication. Making a well-informed investment decision requires obtaining detailed information. Please read the Key Information Document, the official prospectus, and the management regulations available at the distribution points of the Fund and on the website of the Fund Manager (www.vigam.hu) for detailed information regarding the Fund’s investment policy, distribution costs, and the possible risks of investing. Costs related to the distribution of the investment fund (purchase, holding, sale) can be found in the Fund’s management regulations and at the distribution points. Past performance is not a reliable indicator of future returns. Future returns from the investment may be subject to taxation, and tax and duty information relating to individual financial instruments and transactions can only be accurately assessed based on the individual circumstances of each investor, which may change in the future. It is the investor’s responsibility to obtain information regarding tax obligations.
The data contained in this information material are provided for informational purposes only and do not constitute investment advice, an offer, or investment consulting. VIG Investment Fund Management Hungary Ltd. accepts no liability for investment decisions made based on this information or for their consequences. The license number of the Fund Manager for alternative investment fund management (AIFM) is: H-EN-III-6/2015. The license number of the Fund Manager for UCITS fund management (collective portfolio management) is: H-EN-III-101/2016.